NCRTC Corridor Survey — Sarai Kale Khan to Sonipat

Railways & Metro · Delhi to Sonipat border, Haryana

ClientNCRTC, through Mega Engineers, Noida Scope30 km new rail alignment corridor survey

Project Overview

BTPL carried out the topographic corridor survey for a new rail alignment for NCRTC, through Mega Engineers, Noida, extending approximately 30 km from Sarai Kale Khan in Delhi to the Sonipat border in Haryana. The survey covered the corridor width required for alignment studies, capturing ground levels, existing structures, crossings, utilities and boundary detail on a single continuous control framework. The output was prepared as a chainage-referenced dataset suitable for direct use in alignment design.

Client Requirement

The corridor survey was required to provide a continuous and dimensionally reliable base along the proposed route, so that horizontal and vertical alignment could be developed and every interface with existing infrastructure identified. The data was also needed to inform assessment of the land extent involved and to bring out conflicts with existing roads, rail lines, drains and utility corridors. Because the corridor spans two jurisdictions, all data had to sit on one consistent horizontal and vertical datum from end to end.

Project Challenge

  • Maintaining a single consistent horizontal and vertical framework across 30 km of corridor crossing the administrative boundary between Delhi and Haryana
  • Built-up urban stretches with restricted and permission-dependent access to private land, occupied plots and secured premises
  • Survey work alongside live traffic on busy carriageways and at road crossings, requiring short working windows, traffic-aware setups and safety cover for field crews
  • GNSS multipath and signal obstruction near flyovers, high-rise development, overhead power lines and existing rail and metro structures, requiring conventional traversing to bridge affected sections
  • Crossings of drains, canals, service corridors and existing rail infrastructure, each needing detailed capture of levels, clearances and structural extents

BTPL Approach

A primary GNSS control chain was established along the length of the corridor at regular intervals and connected by precise levelling so that every survey party worked to the same horizontal and vertical framework. Control was densified by closed traverses through built-up and obstructed stretches where satellite observation was unreliable, giving continuous coverage without breaking the datum. Detail survey was then executed by total station and RTK, with the corridor divided into manageable reaches and adjacent reaches deliberately overlapped so that the work of separate crews could be compared. Constrained locations — carriageway crossings, live rail interfaces and congested junctions — were surveyed in agreed working windows with the necessary permissions in place, and all reaches were finally merged into one chainage-referenced corridor model.

Data Processing

GNSS baselines and traverse observations were processed and adjusted as a single network before detail data was accepted, with the level network adjusted independently and carried through the full corridor. Coded field data was assembled into continuous strings and surfaces, from which the strip plan, Digital Terrain Model, longitudinal section and cross-sections were generated against the agreed chainage. Structures, utilities and crossings were compiled as separate identified layers so that design interfaces can be isolated from general topography.

Quality Control

Traverses and level runs were closed onto independent control, and levelling was double-run so that misclosure could be assessed against accepted survey practice before acceptance. Detail was verified by observing independent check points from separate setups, and overlapping reaches surveyed by different crews were compared to confirm agreement along the corridor. Feature coding and structure attributes were checked in the field against the compiled plan, and cross-sections were reviewed against observed ground levels before issue.

Result

The survey was delivered through Mega Engineers, Noida for NCRTC as a continuous, chainage-referenced record of the 30 km corridor held on one consistent datum, allowing horizontal and vertical alignment to be developed without gaps or datum breaks between reaches. The structure, utility and crossing inventory gives the design and land teams a clear view of the existing interfaces along the route, supporting land requirement assessment and early resolution of conflicts.

Total station observation on an urban transport corridor — BTPL fieldwork, representative of this survey type
Total station observation on an urban transport corridor — BTPL fieldwork, representative of this survey type
Client

NCRTC, through Mega Engineers, Noida

Technology Used
GNSS DGPS and RTK controlTotal station traversing and detail surveyPrecise digital levellingCAD and GIS corridor mapping
Key Deliverables
Chainage-referenced topographic strip plan of the 30 km corridor in CADLongitudinal section along the surveyed corridorCross-sections at regular chainage intervals and at major crossingsControl point and benchmark register with coordinates, levels and station descriptionsDigital Terrain Model of the surveyed corridor widthInventory of existing structures, road and rail crossings, utilities and drainage features along the corridorSurvey report covering control, datum, methodology and processing
Project gallery

Deliverable extracts (orthomosaic, terrain, CAD) will be added once cleared for publication (client-sensitive information removed per BTPL policy).

Planning a Similar Project?

Share your location, scope and required deliverables — BTPL will propose the appropriate survey methodology.